Since 2013, Sagat Energy launched the power expansion project from 2 to 11 MW.

In 2014, at the construction site were installed: metal-clad switchgear 10 kV and for auxiliary, gas control points, 9 similar gas-piston engines «Waukesha APG 1000 16V150LTD».

We are planning to complete the following scope of works by April 2016:
- Cabling to all stations connected to the metal-clad switchgear 10 kV;
- Installation of transformers 11x1250 0.4 kVA / 10 kV, 2x16 000 kVA 10/10 kV;
- Connection to national networks 220/110/30/10 kV substation KEGOC (Atyrau-220);
- Commissioning and testing for all 11 CHP units with integrated automated control systems.

 

  NON TECHNICAL SUMMARY.

EBRD supports efficient electricity generation in Atyrau